Vigliena reclamation basin – Darsena di Levante

A new 290 m combined retaining wall to make safe again a 43,000 m² basin intended for dredged sediments.

Client
Autorità di Sistema Portuale del Mar Tirreno Centrale (in raggruppamento)
Period
2022 – 2026
Works value
€ 16.763.788Fase 1 – messa in sicurezza della vasca di colmata, lotto 1 (importo contrattuale 17,2 M€). Rimozione del deposito temporaneo di Vigliena: 12,6 M€ (2023-24).
Port / location
Napoli
Sector
Dredging, reclamation and environment

Project review, detailed design, works supervision, health & safety coordination and environmental monitoring for the reinstatement of the Vigliena reclamation basin in the port of Naples, a prerequisite for the completion of the Darsena di Levante.

  1. 01

    The context

    The Vigliena reclamation basin – two cells totalling 43,000 m² – had been severely damaged by wave action: collapsed retaining wall, torn-away steel elements, irregular seabed. Without cell 2 the dredging of the port seabed, and therefore the completion of the Darsena di Levante terminal, is not possible.

    After
    Before
    Drag to compare before and after
  2. 02

    The design

    The design reinstates the containment with a new combined retaining wall set 6 m forward of the existing one: Ø1219 mm tubular piles, AZ 18/700 sheet piles and a coping beam at +3.00 m, with a second row of raking piles stiffening the whole. The structure, about 290 m long, is divided into three sections sized for the different depths and load levels. Cell 1 was fitted with HDPE liners and granular-fill yards.

  3. 03

    The site

    Handover on 4 November 2024, 435 days of works: systematic underwater unexploded ordnance clearance, removal of the wreckage of the old retaining wall, pile driving, vibro-driving of the sheet piles, reinforcement and concreting of the piles. SISPI supervised the works, coordinated health and safety and carried out the post-construction environmental monitoring, with completion within the PNRR deadlines and the structural acceptance test of the works.

The result

A structurally and hydraulically safe reclamation basin, ready to receive the sediments from the dredging of the port of Naples. In parallel SISPI designed the removal of the Vigliena temporary stockpile (M€ 12.6), freeing the areas for the future terminal.

43,000m²the surface area of the basin
290mof new combined retaining wall
Ø1219mmthe tubular piles
435daysthe duration of the works