Projects / Breakwaters and coastal defences
Duca d’Aosta breakwater – strengthening and extension
The main protective barrier of the port of Naples: 2.6 km of breakwater, 860 m of new armour layer in 40 t tetrapods.
- Client
- Autorità di Sistema Portuale del Mar Tirreno Centrale (in raggruppamento)
- Period
- 2023 – in corso
- Works value
- € 80.525.955Lotto B – rafforzamento, I stralcio (L = 850 m). II stralcio (L = 300 m): 25,5 M€, in corso.
- Port / location
- Napoli
Final design, works supervision and health & safety coordination for the strengthening of the breakwater protecting the port of Naples, damaged by the storms of 1987, 1999 and 2020. A strategic structure funded with resources complementary to the PNRR.
-
01
The context
The Duca d'Aosta breakwater, built in several stages over the twentieth century, protects the entire basin of the port of Naples. The storms of December 2020 had caused collapses of the wave wall, openings in the caisson superstructure and widespread cavities: a 2.6 km structure to be made safe without interrupting port operations and within the time constraints of the PNRR.
After
BeforeDrag to compare before and after -
02
The design
The design, developed by SISPI as part of a joint venture, places a new rubble-mound structure on the seaward side of the existing caissons: vibro-replacement of the seabed with gravel columns, a quarry-run bedding layer, a toe berm in 4 m³ tetrapods and a main armour layer in a double layer of 16 m³ (40 t) tetrapods up to a crest level of +6.70 m. In the collapsed sections the wave wall is rebuilt with Ø300 stitching micropiles and in-situ concrete; along the whole 2.6 km the lava-stone copings, stairways and underwater cavities are reinstated. The works are completed by a photovoltaic LED lighting system along the inner edge.
-
03
The site
SISPI supervises the works and coordinates health and safety on a 147,000 m² site that coexists with other interconnected contracts and with port traffic: a 1,000 m³/day concrete batching plant, two tetrapod precasting lines, storage areas for around 645,000 t of rock armour, and a bank of weighbridges for the continuous flow of vehicles. The rubble-mound structure advances in finished 20 m sections, from the bottom upwards, with monitoring of the settlements induced in the existing caissons. The site is documented with periodic drone surveys and time-lapse footage.





The result
Phase 1 (chainage 910–1770 m) gives the port back a breakwater capable of withstanding extreme sea storms and reduces the loads on the historic caissons. Phase 2, covering a further 300 m, is under way. As part of a joint venture SISPI has also signed the final design of the extension (Lot A, M€ 50) and of the strengthening (Lot B, M€ 81) protecting the new eastern container terminal.










Related projects
Napoli2022 – 2026
Vigliena reclamation basin – Darsena di Levante
Dredging, reclamation and environment 17 M€
Napoli2020 – 2025
Pisacane Pier: completion of the strengthening of the eastern quay
Quays, piers and consolidation 18 M€
Napoli2020
New container terminal at the Darsena di Levante – 1 million TEU/year
Terminals and platforms 107 M€