Projects / Quays, piers and consolidation
Extension of the Manfredi Pier for cruise traffic
125 m of new cofferdam quay in front of Zaha Hadid's Maritime Terminal, continuing the section designed and supervised by SISPI in 2013.
- Client
- Autorità di Sistema Portuale del Mar Tirreno Centrale (in raggruppamento)
- Period
- 2023 – 2026
- Works value
- € 13.059.883I fase – stralcio 1. Stabilizzazione del piede della banchina di ponente: 4,2 M€ (2025-26).
- Port / location
- Salerno
Final design, works supervision and health & safety coordination for the extension of Salerno's cruise pier: a double anchored combined-wall structure, anti-reflection cells and new quay furniture, built in an operating port.
-
01
The context
The 2022 Technical and Functional Adjustment of the port of Salerno provides for lengthening the Manfredi Pier as far as the main breakwater to accommodate larger cruise ships. Phase 1 was to add 125 m of quay to the existing section – itself designed and supervised by SISPI in 2013 – while maintaining full use of the turning basin and the adjacent marina.
After
BeforeDrag to compare before and after -
02
The design
The new quay is a double combined-wall cofferdam: HZ 1080 M king piles alternating with AZ 18-700 sheet piles on the western side (design depth −11.50 m) and HZ 880 M on the eastern side (−6.00 m), tied together at the top by 36.5 m long M80 bar anchors. Inside, anti-reflection cells filled with limestone rock mitigate the agitation of the basin; a capping beam on 27 m long Ø1000 piles supports the deck. Coping beams with precast fascia panels, 22 bollards of 100 t, 12 fenders, four lighting towers, impressed-current cathodic protection with SCADA supervision and provision for shore power (cold ironing) complete the works.
-
03
The site
The walls were driven from the sea using a pontoon and variable-frequency vibratory hammers, with monitoring of vibrations on the neighbouring structures. The fill was first placed from the land and then relocated inside the cofferdam after unexploded ordnance clearance. SISPI's works supervision managed a variation and the supplementary agreement for the additional toe protection works to the western quay, bringing the project to final acceptance within the PNRR deadlines.





The result
A quay of 125.25 × 40 m, crest level +1.80 m, depth −11.50 m and bollard pull of 1,000 kN, aligned with the existing pier and ready for new-generation cruise ships. The completed pier now measures over 300 m and represents the third phase of SISPI's work on the Manfredi Pier, which began with the strengthening of the western quay in 2011.